October 22, 2026
The wooden castle at Reaves Park was finished on March 28, 1999. Hundreds of Norman residents built it by hand, and more than $130,000 in private donations paid for it. The bench at the entrance carries hand-painted clay tiles with handprints, drawings and names, made through a fundraiser at Sooner Mall.
That structure is now in its last weeks. The City of Norman held "Kids Space Last Play" on Oct. 11 and broke ground on the replacement on Oct. 19 after rain pushed the ceremony back from Oct. 14. The next Kids Space will go up the same way the first one did. Residents will build it, and the City's project calendar already has their part scheduled for March 2027.
The City's project calendar for the grant runs demolition of the old playground from Nov. 1 to Dec. 30, 2026. Earlier estimates came in a little sooner. OKC Fox reported in September that demolition was expected in October or November. So the start of November is the safest assumption for when the wood starts coming down.
If your family's name is on one of the engraved donor boards from the 1999 build, the deadline is close. Park staff took the boards down at the Last Play event, and the City said it would hold any boards not picked up there for up to 30 days. That puts the end of the hold around Nov. 10. You can schedule a pickup with Norman Parks & Recreation at [email protected] or 405-366-5472.
Some of the old structure is staying in the park. Staff plan to reuse some of the original Kids Space wood in three new shelters around the playground, the Norman Transcript reported. The City's plan also calls for a public art piece honoring the 1999 build and its volunteers, plus new materials designed to look like the wood structure while holding up longer.
All of these dates come from the City's grant project calendar. Every task on it was marked "Not Started" when it was filed, so treat them as the plan for now. They are not confirmed dates.
| Window | What's scheduled |
|---|---|
| Nov. 1 – Dec. 30, 2026 | Old Kids Space demolished |
| Nov. 15 – Dec. 30, 2026 | Phase I playground equipment delivered |
| Jan. 15 – Feb. 15, 2027 | City recruits resident volunteers through press releases and social media |
| Jan. 15 – end of Feb. 2027 | Park Maintenance sets the main supports and piers |
| March 1 – April 1, 2027 | Community build, possibly during Spring Break week |
| April 1 – June 1, 2027 | Contractors install the accessible poured surface |
| June 1 – 15, 2027 | Phase I opens to the public |
The order matters if you want to help. The volunteer call is planned for mid-January, a few weeks before the build. If you missed the sign-up at the Oct. 19 groundbreaking, that January push is the next scheduled chance. The calendar also says residents who join the build can pick up pickets and tiles from the first build.
The community build will not start from bare dirt. Park Maintenance plans to put in the main supports before volunteers arrive. Leathers & Associates is listed as the Year 1 playground-materials vendor and construction consultant. The Transcript says the City is bringing back a weeklong community build in March, modeled on the 1999 build.
Phase I, the part volunteers help build, includes:
The surface is the biggest change you'll notice underfoot. The new playground is meant to be "highly accessible," with poured surfacing in place of wood chips and fake grass, and staff agreed to include a wheelchair-accessible swing. The City's plan calls for a four-foot black vinyl chain-link fence around it.
Phase II starts in September 2027. It adds a tot lot for ages 2 to 5, the public art piece, and the rest of the sidewalk and signage work. The City's Year 2 calendar puts that work between Sept. 1, 2027 and Aug. 31, 2028, so the full Kids Space will take longer than Phase I.
Before the community build starts, students from the University of Oklahoma will be working at the site. The City is partnering with OU's American School of Design-Build program on a new pavilion in the Kids Space area. Architecture and construction science students will design and build it as part of their coursework, and the City will pay for materials. The City expects it to be done in spring 2027. According to the Transcript, the shelter will be about 1,500 square feet, with student work starting in November.
You'll see two opening targets for the new playground, and they come from different places. The City's project calendar has Phase I opening June 1 to 15, 2027. The Transcript reported the City hopes to finish Phase I construction in April 2027, before the Medieval Fair. Both can hold at once. The calendar has the poured surface going in from April into June, after the volunteers finish, so the build itself could wrap up in April even if the gates don't open until June.
An older estimate is out there too. A City release from May 2026 projected completion in summer 2027. The newer calendar splits the project into two phases across two grant years, so plan on summer 2027 for the main playground and later for the tot lot.
The money explains why this is happening now. The City was awarded a $598,000 Built Environment Grant from the Oklahoma Tobacco Settlement Endowment Trust, known as TSET, with the money paid out over two years, one year for each building phase. The Transcript puts the total project at about $1 million. The City only had to put in $119,000 to match the grant, but staff asked for $400,000. Parks and Recreation Director Jason Olsen explained the request to the Council, as the Norman Transcript reported:
"What we're asking for today is $400,000 so that we make sure that we can do this project correct, up to the nicest standard. It is the most important playground in Norman's parks system."
Kids Space is coming down, and Reaves Park still has events on the calendar. Norman's Veterans Day Parade and Celebration is at Reaves Park on Sunday, Nov. 8, at 2 p.m. It includes a parade, guest speakers, a display of military vehicles and daytime fireworks. If you're bringing kids, the parade falls during the demolition window, so the Kids Space area may look very different from last year.
Until the new playground opens, two City parks are the closest match for what Kids Space offers:
Andrews also gives you a preview of the accessible design Kids Space is moving toward. In the City's announcement, Olsen said: "And just like before, this project will be built with the help of our community." For the families who built the first Kids Space in 1999, the schedule above shows when they can help build the second.
If you have Kids Space memories, or you're planning a family trip around the March build week, I'd love to hear about it. I keep up with what's changing in Norman parks because it's part of what makes a house feel like home here. Reach out to Jennifer Elliston and let's connect.